Exterior Damage caused by Hurricane
Georges was extensive. It was so extensive that the patching of the
E.I.F.S. without visually recognizing the patches was impossible. To
mask the repairs a high build 100% Silicone Elastomeric system, of
multiple colors, was applied to all exterior surfaces of the Casino,
Lowrise Facility and the Highrise Hotel. The Hurricane struck during
construction with a opening date scheduled and publicized. This made
this project accelerated resulting in a 24 hour day and 7 day week
schedule. To reach the surfaces an elaborate system of suspended
stages, scaffolds, manlifts and barges was employed. All of this
work was performed in the final stages of construction of this
massive project when normal finishing touches are being made such as
landscaping, staining concrete and paving.
|
|