The surface preparation and painting
of this project consisted of blasting and applying an Epoxy/Urethane
system to 225,000 square feet of extremely deteriorated steel having
multiple coats of failed paint on a Ro-Ro type vehicle
transportation barge. The key to this project was that the barge was
in a cycle-delivery system of two-week intervals. This dictated that
the entire scope had to be completed and cured within a one-cycle
period. Two crews of 50+ men, working around the clock in 12-hour
shifts, diligently accomplished the task, receiving great reviews
from the customer.
|
|